| STUDY OF DEFORMATION AND CRACKING MECHANISM OF SURROUNDING ROCK OF JINPING I UNDERGROUND POWERHOUSE |
| (1. Key Laboratory of Geotechnical Mechanics and Engineering of the Ministry of Water Resources,Yangtze River Scientific Research Institute,Wuhan,Hubei 430010,China;2. Jinping Construction Bureau,Ertan Hydropower Development Co.,Ltd.,Chengdu,Sichuan 610021,China) |
|
|
|
|
Abstract Aiming at the deformation and cracking phenomena of surrounding rock mass during the excavation of Jinping I hydropower station underground powerhouse under the conditions of high stress and low strength stress ratio,the characteristics and laws of in-situ stress field are studied entirely by the stereographic projection method and projection stress on typical planes. The deformation and cracking mechanism of surrounding rock of underground caverns group are deeply analyzed through mechanical qualitative analysis and 3D numerical simulation;and the damage evolution law of surrounding rock is studied. The results show that the relatively large deformation and cracking phenomena of surrounding rock and shotcrete layer of underground powerhouse are caused essentially by the adverse combination of the high ground stress and relatively low rock strength. The cracking failures in haunch,arch abutment and side wall of main powerhouse and main transformer chamber,and in side wall of busbar tunnels are typical unloading deformations and failures under the conditions of high stress,low strength stress ratio. The generalized model of surrounding rock deformation and cracking of underground powerhouse is presented. It affords important reference and qualitative basis for the back analysis of in-situ stress field and the numerical simulation of excavation process. Finally,some advices are given to maintain the stability of surrounding rock mass. All the results afford technical support to the construction and dynamic support design of the underground powerhouse.
|
|
Received: 02 June 2010
|
|
|
|
| [1] 郑汉淮,杨静熙,邓卫东,等. 雅砻江锦屏一级水电站可行性研究报告(工程地质)[R]. 成都:中国水电工程顾问集团成都勘测设计研究院,2003.(ZHENG Hanhuai,YANG Jingxi,DENG Weidong,et al. Feasibility study report of Jinping I hydropower project located on Yalong River(Engineering Geology)[R]. Chengdu:HydroChina Chengdu Hydroelectric Investigation and Design Institute,2003.(in Chinese))
[2] 周 钟,汤雪峰,廖成刚,等. 雅砻江锦屏一级水电站地下厂房洞室群围岩稳定与支护、厂房主要结构设计报告[R]. 成都:中国水电工程顾问集团成都勘测设计研究院,2007.(ZHOU Zhong,TANG Xuefeng,LIAO Chenggang,et al. Report on surrounding rock mass stability and support,main structures design for underground powerhouse caverns group of Jinping I hydropower project located on Yalong River[R]. Chengdu:HydroChina Chengdu Hydroelectric Investigation and Design Institute,2007.(in Chinese))
[3] 周 钟,巩满福,侯东奇,等. 四川省雅砻江锦屏一级水电站地下厂房洞室群施工期围岩稳定与支护设计报告(4)[R]. 成都:中国水电顾问集团成都勘测设计研究院,2008.(ZHOU Zhong,GONG Manfu,HOU Dongqi,et al. Report on surrounding rock mass stability and support design for underground powerhouse caverns group construction of Jinping I hydropower project located on Yalong River(4)[R]. Chengdu:HydroChina Chengdu Hydroelectric Investigation and Design Institute,2008.(in Chinese))
[4] 陈赛超,董燕君,鲁晓明,等. 锦屏一级水电站引水发电系统及地下厂房安全监测专题报告[R]. 锦屏:锦屏建设管理局锦屏一级安全监测管理中心,2009.(CHEN Saichao,DONG Yanjun,LU Xiaoming,et al. Special report on safety monitoring for water diversion and power generation system and underground powerhouse of Jinping I hydropower project[R]. Jinping:Jinping I Safety Monitoring and Management Center of Jinping Construction Bureau,2009.(in Chinese))
[5] 中国水电工程顾问集团成都勘测设计研究院. 锦屏一级水电站地下厂房洞室群围岩岩体质量物探检测阶段成果报告[R]. 成都:中国水电工程顾问集团成都勘测设计研究院,2009.(HydroChina Chengdu Hydroelectric Investigation and Design Institute. Stage report on surrounding rock mass quality geophysical detection for underground powerhouse caverns group of Jinping I hydropower project[R]. Chengdu:HydroChina Chengdu Hydroelectric Investigation and Design Institute,2009.(in Chinese))
[6] 李仲奎,周 钟,汤雪峰,等. 锦屏一级水电站地下厂房洞室群稳定性分析与思考[J]. 岩石力学与工程学报,2009,28(11):2 167–2 175.(LI Zhongkui,ZHOU Zhong,TANG Xuefeng. Stability analysis and considerations of underground powerhouse caverns group of Jinping I hydropower station[J]. Chinese Journal of Rock Mechanics and Engineering,2009,28(11):2 167–2 175.(in Chinese))
[7] 丁秀丽,卢 波,黄书岭,等. 雅砻江锦屏一级水电站技施阶段——高应力低强度应力比条件大型地下洞室群围岩开裂变形机制及稳定性研究[R]. 武汉:长江科学院,2010.(DING Xiuli,LU Bo,HUANG Shuling,et al. Technical construction stage of Jinping I hydropower station on Yalong River—research on stability and fracturing mechanism of surrounding rock mass for large underground powerhouse under conditions of high in-situ stress and low strength stress ratio[R]. Wuhan:Yangtze River Scientific Research Institute,2010.(in Chinese))
[8] 谷兆祺,彭守拙,李仲奎. 地下洞室工程[M]. 北京:清华大学出版社,1994.(GU Zhaoqi,PENG Shouzhuo,LI Zhongkui. Underground caverns engineering[M]. Beijing:Tsinghua University Press,1994.(in Chinese))
[9] HOEK E,BROWN E T. 岩石地下工程[M]. 连志升译. 北京:冶金工业出版社,1986.(HOEK E,BROWN E T. Underground excavation in rock[M]. Translated by LIAN Zhisheng. Beijing:Metallurgical Industry Press,1986.(in Chinese))
[10] 董学晟,田 野,邬爱清. 水工岩石力学[M]. 北京:中国水利水电出版社,2004.(DONG Xuesheng,TIAN Ye,WU Aiqing. Rock mechanics in hydraulic engineering[M]. Beijing:China Water Power Press,2004.(in Chinese)) |
|
|
|