| STUDY OF ESTABLISHED MECHANISM AND SETTING STANDARD OF CHAMBER EARTH PRESSURE FOR EARTH PRESSURE BALANCE SHIELD |
| HOU Yongmao1,2,YANG Guoxiang2,GE Xiurun1,ZHENG Yifeng2,GU Chenying2 |
(1. School of Naval Architecture,Ocean and Civil Engineering,Shanghai Jiaotong University,Shanghai 200240,China;
2. Shanghai Tunnel Engineering Co.,Ltd.,Shanghai 200082,China) |
|
|
|
|
Abstract The chamber earth pressure control is a key operation for controlling the impact of the earth pressure balance(EPB) shield excavation on the environment. Based on Shanghai Yingbinsanlu tunnel project constructed by a super-diameter EPB shield,the established mechanism and setting standard of the chamber earth pressure are studied by the theoretical research and measured data analysis. Relationships of the shield construction parameters are studied based on the soil in-out balance concept. The established mechanism of the chamber earth pressure is revealed according to introduce the soil compressing amount at the excavation face. A detailed model of shield cutter head is introduced to analyze the soil compressing amount at the excavation face caused by the cutter head. Based on the concept of controlling the secondary disturbance of the soil at the excavation face,a setting standard of the chamber earth pressure is proposed. The research results are applied and verified in the super-diameter tunnel,monitoring data shows that the settlement caused by shield tunneling construction is controlled effectively.
|
|
Received: 15 September 2011
|
|
|
|
| [1] MAIR R J,TAYLOR R N. Bored tunneling in the urban environment[C]// Proceedings of the 14th International Conference on Soil Mechanics and Foundation Engineering. Hamburg:A. A. Balkema,1997:2 353–2 380.
[2] ATKINSON J H,POTTS D M. Stability of a shallow circular tunnel in cohesionless soil[J]. Geotechnique,1977,27(2):203–215.
[3] ANAGNOSTOU G,KOVARI K. Face stability conditions with earth-pressure-balanced shields[J]. Tunnelling and Underground Space Technology,1996,11(2):165–173.
[4] 魏建华,丁书福. 土压平衡式盾构开挖面稳定机制与压力舱土压的控制[J]. 工程机械,2005,(1):18–19.(WEI Jianhua,DING Shufu. Excavating face stabilization mechanism of soil pressure balance shield and control of soil pressure in pressure cabin[J]. Construction Machinery and Equipment,2005,(1):18–19.(in Chinese))
[5] 王洪新,傅德明. 土压平衡盾构掘进的数学物理模型及各参数间关系研究[J]. 土木工程学报,2006,39(9):86–90.(WANG Hongxin,FU Deming. A mathematical model and related parameters for EPB shield tunneling[J]. China Civil Engineering Journal,2006,39(9):86–90.(in Chinese))
[6] 王洪新. 土压平衡盾构刀盘挤土效应及刀盘开口率对盾构正面接触压力影响[J]. 土木工程学报,2009,42(7):113–118.(WANG Hongxin. Effect of cutter head compressing the front soil and influence of head aperture ratio on contact pressure of EPB shield to the front soil[J]. China Civil Engineering Journal,2009,42(7):113–118.(in Chinese))
[7] 上官子昌,李守巨,孙 伟,等. 土压平衡盾构机密封舱土压力控制方法[J]. 煤炭学报,2010,35(3):402–405.(SHANGGUAN Zichang,LI Shouju,SUN Wei,et al. Controlling earth pressure of head chamber of earth pressure balance(EPB) shield machine[J]. Journal of China Coal Society,2010,35(3):402–405.(in Chinese))
[8] 施 虎,龚国芳,杨华勇,等. 盾构掘进机推进力计算模型[J]. 浙江大学学报:工学版,2011,45(1):126–131.(SHI Hu,GONG Guofang,YANG Huayong,et al. Determination of thrust force for shield tunneling machine[J]. Journal of Zhejiang University:Engineering Science,2011,45(1):126–131.(in Chinese))
[9] 沈建奇,金先龙,杨建刚,等. 盾构机刀盘掘削动态数值模拟[J]. 上海交通大学学报,2009,43(6):1 017–1 020.(SHEN Jianqi,JIN Xianlong,YANG Jiangang,et al. Dynamic numerical simulation of excavation in shield tunnelling[J]. Journal of Shanghai Jiaotong University,2009,43(6):1 017–1 020.(in Chinese)) |
| [1] |
MAO Yuting1, 2, HE Manchao1, 2, LIU Fangzhou3, BAI Xing4, YANG Xiaojie1, 2, TAO Zhigang1, 2*. Development and application of a large-scale physical model system for tunnel creep testing[J]. , 2026, 45(6): 1627-1638. |
|
|
|
|