Abstract Tieshan tunnel of the Bapeng road is located in Daxiang of Shichuan province with the total length of 2 099 m. The tunnel passes through coal mined-out area K17-1,K21 and K24. The deformation,cracking,alteration and falling occur at the secondary lining at the station of K140+527~608 due to the influence of mined-out area,underground water and other factors,which do harm to the traffic safety,and must be cured. The stability of roof rocks of mined-out area is analysed according to engineering geological conditions and the reinforcement technology of mined-out area is presented.
|
|
|
|
|
1[ |
苏] 鲍里索夫 A A. 矿山压力原理与计算[M]. 北京:煤炭工业出版社,1986,13~14
|
2常 |
士骠. 工程地质手册[M]. 北京: 中国建筑工业出版社,1997,215~216
|
3[ |
日]草野一人. 地基加固和防水注浆设计施工手册[M]. 北京:中国铁道出版社,1989,22~23
|
4梁 |
炯鋆. 锚固与注浆技术手册[M]. 北京:中国电力出版社,1999,354~354
|
5郝 |
哲,王介强,刘 斌. 岩体渗透注浆的理论研究[J]. 岩石力学与工程学报,2001,20(4):492~496
|
|
|
|