ANALYSIS OF EXCAVATION MONITORING FOR DEEP FOUNDATION PIT IN XIAMEN WUCUN TUNNEL
PANG Tiezheng1,2,FANG Yongsheng3,QIN Weimin4
(1. Engineering Research Center of Tunnel and Underground Engineering,Ministry of Education,Beijing Jiaotong University,Beijing 100044,China;2. Xiamen Road and Bridge Construction Group Co.,Ltd.,Xiamen,Fujian 361026,China;3. Water Resources Bureau of Xianning,Xianning,Hubei 437100,China;4. State Key Laboratory of Geomechanics and Geotechnical Engineering,Institute of Rock and Soil Mechanics,Chinese Academy of Sciences,Wuhan,Hubei 430071,China)
Abstract:Taking the deep foundation pit of open-cut tunnel in Xiamen City for example,safety monitoring is carried out on the surrounding environment as well as on supporting structure itself during the construction period. The monitoring measures for the safe construction of deep foundation pit mainly include tour check,settlement,horizontal displacement,deep displacements,underground water level,axial stress of anchor and blasting vibration,etc.. Combined with the geology condition and in-situ construction environment,the monitoring results are comprehensively analyzed on the surrounding environment as well as on supporting structure. Research results show that geology condition is the main factor that causes the difference of deformation distribution. Large displacement will appear after the creation of new free face,so the stability of the retaining pile are affected. When the blasting excavation is applied on the deep foundation pit,the selection of design parameters are demanded to further verify their rationality. Monitoring and analysis are carried on dangerous situation such as high displacement velocity of the supporting pile,landslide and collapse of slope etc.;and the monitoring results show that emergency measures relevant to the dangerous situation are reasonable and effective.
逄铁铮1,2,方勇生3,覃卫民4. 厦门梧村隧道明挖深基坑施工监测分析[J]. 岩石力学与工程学报, 2013, 32(s1): 2751-2757.
PANG Tiezheng1,2,FANG Yongsheng3,QIN Weimin4. ANALYSIS OF EXCAVATION MONITORING FOR DEEP FOUNDATION PIT IN XIAMEN WUCUN TUNNEL. , 2013, 32(s1): 2751-2757.
中华人民共和国行业标准编写组. GJ120—99 建筑基坑支护技术规程[S]. 北京:冶金工业出版社,1999.(The Professional Standards Compilation Group of Peoples Republic of China. JGJ120—99 Technical specification for retaining and protection of building foundation excavation[S]. Beijing:China Metallurgical Industry Press,1999.(in Chinese))