(1. Yalong River Hydropower Development Company,LTD,Chengdu 610051,China;2. Institute of Rock and Soil Mechanics,Chinese Academy of Sciences,Wuhan 430071,China;3. Shenyang Railway Survey Design Consulting Company Limited,Shenyang 110013,China)
Abstract:To improve efficiency of construction and reduce the risk of site construction personnel and equipment,the 1#,3# diversion tunnel of Jinping II hydropower station adopt large-section TBM for construction. The full-section TBM construction under large buried depth,when encounter strong grade rock burst,it still may bring some damage to TBM equipment. Therefore,through the real time microseismic monitoring and numerical analysis,study the influence of TBM excavation scheme、heading construction on the risk of rock burst. The results show that,lowering the rate of construction,can reduce the risk of rock burst;pilot excavation and TBM joint construction is advantageous to prevent strong grade rock burst. The research results can provide important reference value for the safe and rapid excavation of TBM,will also provide reference for other similar project,it has an important engineering value.
吴世勇1,周济芳1,陈炳瑞2,黄满斌3. 锦屏二级水电站引水隧洞TBM开挖方案对岩爆风险影响研究[J]. 岩石力学与工程学报, 2015, 34(04): 728-734.
WU Shiyong1,ZHOU Jifang1,CHEN Bingrui2,HUANG Manbin3.
RESEARCH ON EFFECTIONS OF EXCAVATION SCHEMES OF TBM ON RISK OF ROCK BURST OF LONG POWER TUNNELS OF JINPING II HYDROPOWER STATION. , 2015, 34(04): 728-734.
吴世勇,周济芳. 锦屏二级水电站长引水隧洞高地应力下开敞式硬岩隧道掘进机安全快速掘进技术研究[J],岩石力学与工程学报,2012,30(1):149-154.(WU Shiyong,ZHOU Jifang. Research on safe and fast tunneling technology by open-type hard rock tbm under high geostress of long diversion tunnels of jinping ii hydropower station[J]. Chinese Journal of Rock Mechanics and Engineering,2012,30(1):149-154.(in Chinese))