Abstract:This paper described the optimazation analysis of reinforcing scheme for underground power house of Shuibuya Project. In 2D analysis the comparison of rock condition for case nonreinforcement and case with reinforcement has been made, and of rock condition for different initial stress has been made as well. Three different schemes for systematical rock bolts were compared. In 3D analysis the comparison of reinforcing effect for 3 schemes of prestress cable with different tonnage has been conducted. Some relevant conclusions were given finally.
收稿日期: 2003-03-31
引用本文:
朱维申;李术才;陈卫忠;孙静. 清江水布垭工程地下厂房围岩锚固方案优化研究[J]. 岩石力学与工程学报, 2003, 22(S1): 2127-2131.
Zhu Weishen1 Chen Weizhong2 Li Shucai1 SunJin2. OPTIMAZATION OF REICNFORING SCHEME FOR UNDERGROUND POWER HOUSE OF SHUIBUYA PROJECT ON QINJANG RIVER. , 2003, 22(S1): 2127-2131.