| STUDY OF TBM CONSTRUCTION OF DIVERSION TUNNEL FOR JINPING II HYDROPOWER STATION |
(1. School of Water Resources and Hydropower,Wuhan University,Wuhan,Hubei 430072,China;2. Ertan Hydropower Development Company,Ltd.,Chengdu,Sichuan 610051,China;3. East China Investigation and Design Institute,China Hydropower Engineering Consulting Group Co.,Hangzhou,Zhejiang 310014,China;4. State Key Laboratory of Geomechanics and Geotechnical Engineering,Institute of Rock and Soil Mechanics,Chinese Academy of Sciences,Wuhan,Hubei 430071,China;5. Key Laboratory of Urban Security and Disaster Engineering of Ministry of Education,Beijing University of Technology,
Beijing 100124,China) |
|
|
|
|
Abstract The diversion tunnel for Jinping II Hydropower Station is currently the largest group of hydropower tunnels in China. The surrounding rock masses of the tunnel are of long length,deep embedded depth and technical difficulties of construction,which is a variety of geological hazards such as water bursting,rockburst,collapse and so on. It is necessary to choose the safe and rapid excavation technology for ensuring construction safety and power generation schedule,so a large number of studies and analysis of the technology of TBM construction is conducted;and the results are as follows:TBM construction method is feasible not only in the view of rock drillability and cutter wear but also from rock deformation and fracture;but it is some advantage for the traditional drill and blast method to deal with issues such as groundwater,rockburst,large deformation and so on,and which has a better protective effect in the personnel safety. It can do better in solving a series of engineering problems on the construction process if using the continuous improvement of construction technology and supporting tools which come from between geological prediction and construction.
|
|
Received: 25 June 2010
|
|
|
|
| [1] 瑞士安伯格工程咨询公司. 锦屏二级长引水隧洞采用TBM施工可行性咨询报告[R]. 瑞士:安伯格工程咨询公司,2006.(Am Berg Technologis Ltd. Feasibility consultation report on TBM working for Jinping Cascade-II Hydropower Station with long diversion tunnel[R]. Switzerland:Am Berg Technologies Ltd.,2006.(in Chinese))
[2] 水利部科技推广中心. 全断面岩石掘进机[M]. 北京:石油工业出版社,2005:8.(Extension Center for Science and Technology Ministry of Water Resources,PRC. Full face TBM for hard rocks[M]. Beijing:Petroleum Industry Press,2005:8.(in Chinese))
[3] 隆 威,尹俊涛,刘永正,等. TBM掘进技术的发展应用及相关工程地质问题探讨[J]. 探矿工程(岩土钻掘工程),2005,32(2):55–59.(LONG Wei,YIN Juntao,LIU Yongzheng,et al. The development and application of TBM,and discussion of correlated engineering geological problems[J]. Exploration Engineering(Rock and Soil Drilling and Tunnelling),2005,32(2):55–59.(in Chinese))
[4] 张可诚,曾金富,张 杰,等. 秦岭隧道掘进机通过岩爆地段的对策[J]. 世界隧道技术,2000,21(4):34–38.(ZHANG Kecheng,ZENG Jinfu,ZHANG Jie,et al. Countermeasures for TBM passing through rock-blasting section in Qinling tunnel[J]. Modern Tunnelling Technology,2000,21(4):34–38.(in Chinese))
[5] 梁晋平,李文全,史国珍. 双护盾全断面掘进机在万家寨引黄工程中的应用[J]. 现代隧道技术,2001,38(4):27–36.(LIANG Jinping,LI Wenquan,SHI Guozhen. Application of double shield TBM in Wanjiazai diversion works[J]. Modern Tunnelling Technology,2001,38(4):27–36.(in Chinese))
[6] 刘冀山,肖晓春,杨洪杰,等. 超长隧洞TBM施工关键技术研究[J]. 现代隧道技术,2005,42(4):37–43.(LIU Jishan,XIAO Xiaochun,YANG Hongjie,et al. A study on key construction techniques for tunnel boring machines adopted in super-long tunnels[J]. Modern Tunnelling Technology,2005,42(4):37–43.(in Chinese))
[7] 姜 曦,王成端. TBM隧道掘进法出渣系统优化配置分析[J]. 矿山机械,2005,(6):8–9.(JIANG Xi,WANG Chengrui. Analysis of optimization configuration for slag-tapping system of TBM[J]. Mining and Processing Equipment,2005,(6):8–9.(in Chinese))
[8] BRULAND A. Hard rock tunnel boring[Ph.D.Thesis][D]. Trondheim:Norwegian University of Science and Technology,1998.
[9] 王梦恕,李典璜,张镜剑,等. 岩石隧道掘进机(TBM)施工及工程实例[M]. 北京:中国铁道出版社,2004.(WANG Mengshu,LI Dianhuang,ZHANG Jingjian,et al. Tunnelling with rock TBM and related case studies[M]. Beijing:China Railway Publishing House,2004.(in Chinese))
[10] 中国水电顾问集团华东勘测设计研究院. 锦屏二级电站可行性研究报告[R]. 杭州:中国水电顾问集团华东勘测设计研究院,2005.(East China Investigation and Design Institute under CHECC. Feasibility study report on Jinping II Hydropower Station[R]. Hangzhou:East China Investigation and Design Institute under CHECC,2005.(in Chinese))
[11] 陈炳瑞. 岩石工程长期稳定性智能反馈分析方法及应用研究[博士学位论文][D]. 沈阳:东北大学,2007.(CHEN Bingrui. Study on intelligent back analysis method for long-term stability of rock engineering and its applications[Ph. D. Thesis][D]. Shenyang:Northeastern University,2007. |
|
|
|