| GROUND SETTLEMENT DEFORMATION CHARACTERISTIC
STUDY OF SHALLOW LARGE-SPAN TUNNEL IN CONSTRUCTION PROCESS |
| LI Xinzhi,LI Shucai,LI Shuchen |
| (Geotechnical and Structural Engineering Research Center,Shandong University,Jinan,Shandong 250061,China) |
|
|
|
|
Abstract According to Mulingguan tunnel of Qingzhou to Linshu highway,the monitoring of ground settlement deformation characteristic on the shallow large-span tunnel in the construction process was carried out,the excavation methods of the three-lane span shallow tunnel were discussed and tunnel ground settlement deformation characteristic under the three-level seven-step parallel tunnel excavation was analyzed. Through field test discovered in the process of the pile roof and before the excavating face,the ground had occurred beforehand settlement displacement. The key step influenced ground deformation near the tunnel center line was first and middle step,then the key step influenced ground deformation near the tunnel arch shoulder was down and last step,it showed that with the tunnel excavation depth increases,the range and depth of its impact on both sides of the tunnel extension. The impact of tunnel excavating face on ground settlement focused on the excavating face within 1 times of the hole diameter D,afterward excavating face one D,the deformation gradually slowed down,and the eventually ground settlement distribution appeared abnormal skewness to the first excavating tunnel. Three-dimensional fast Lagrangian element method was applied to simulate the excavation of shallow large-span tunnel tunnel. The distributions of ground settlement were obtained and the result was in good agreement with that of in-situ monitoring test,the conclusions can provide a reference for other similar projects.
|
|
Received: 18 February 2011
|
|
|
|
| [1] KARMEN F B,BORUT P. Displacement analysis of tunnel support in soft rock around a shallow highway tunnel at Golovec[J]. Engineering Geology,2004,75(1):89–106.
[2] TESTUO I,WATARU A,HIROMICHI S,et al. Estimation of natural ground behavior ahead of face by measuring deformation which utilized TBM drift tunnel[J]. Tunnelling and Underground Space Technology,2004,19(4/5):527–528.
[3] 刘招伟,何满潮. 肖红渠. 浅埋大跨连拱隧道施工中变形的监测与控制措施[J]. 岩土工程学报,2003,25(5):339–342.(LIU Zhaowei,HE Manchao,XIAO Hongqu. Deformation monitoring and control measures of shallow large-span duel-linked arch tunnel[J]. Chinese Journal of Geotechnical Engineering,2003,25(5):339–342.(in Chinese))
[4] 汪振伟,城市连拱隧道施工地表沉降研究[硕士学位论文][D]. 重庆:重庆交通大学,2008.(WANG Zhenwei. Study on the surface subsidence caused by construction of urban double-arched tunnel[M. S. Thesis][D]. Chongqing:Chongqing Jiaotong University,2008.(in Chinese))
[5] 施成华,彭立敏,刘宝琛. 浅埋隧道开挖对地表建筑物的影响[J]. 岩石力学与工程学报,2004,23(19):3 310–3 316.(SHI Chenghua,PENG Limin,LIU Baochen. Influence of shallow tunnel excavation on ground surface buildings[J]. Chinese Journal of Rock Mechanics and Engineering,2004,23(19):3 310–3 316.(in Chinese))
[6] 陈 虹. 城市浅埋大跨隧道钻爆法施工地层变形规律研究[硕士学位论文][D]. 成都:西南交通大学,2005.(CHEN Hong. Research of the strata deformation rule of shallow rock and large span tunnel in city constructed using drill-blasting method[M. S. Thesis][D]. Chengdu:Southwest Jiaotong University,2005.(in Chinese))
[7] 陈 敬. 大跨浅埋隧道的地表变形数据分析[硕士学位论文][D]. 南京:东南大学,2005.(CHEN Jing. The ground settlement data analysis of large-span shallow tunnel[M. S. Thesis][D]. Nanjing:Southeast University,2005.(in Chinese))
[8] 丁文其,王晓形,李志刚,等. 龙山浅埋大跨度连拱隧道施工方案优化分析[J]. 岩石力学与工程学报,2005,24(22):4 042–4 047. (DING Wenqi,WANG Xiaoxing,LI Zhigang,et al. Optimal analysis of construction schemes for shallow large-span Longshan twin tunnel[J]. Chinese Journal of Rock Mechanics and Engineering,2005,24(22):4 042–4 047.(in Chinese))
[9] 梁 巍,黄明利. 大跨度隧道CRD法穿越含水软弱层沉降变形控制[J]. 岩石力学与工程学报,2007,26(增2):3 738–3 742.(LIANG Wei,HUANG Mingli. Subsidence and deformation control of large- span tunnel in water-bearing unfavorable geological conditions[J]. Chinese Journal of Rock Mechanics and Engineering,2007,26(Supp.2):3 738–3 742.(in Chinese))
[10] 丁建隆. 浅埋大跨度隧道的合理施工工法[J]. 中国铁道科学,2005,26(4):77–81.(DING Jianlong. Reasonable method for the construction of shallow-depth and wide-span tunnel[J]. China Railway Science,2005,26(4):77–81.(in Chinese))
[11] 阳军生,刘宝琛. 城市隧道施工引起的地表移动及变形[M]. 北京:中国铁道出版社,2002:25–28.(YANG Junsheng,LIU Baochen. Surface movement and deformation due to city tunneling excavation[M]. Beijing:China Railway Publishing House,2002:25–28.(in Chinese))
[12] 周丁恒,曲海锋,蔡永昌,等. 特大断面大跨度隧道围岩变形的现场试验研究[J]. 岩石力学与工程学报,2009,28(9):1 773–1 782. (ZHOU Dingheng,QU Haifeng,CAI Yongchang,et al. In-situ test on surrounding rock deformation in super-large section and large-span tunnel[J]. Chinese Journal of Rock Mechanics and Engineering,2009,28(9):1 773–1 782.(in Chinese))
[13] 蒋树屏,赵 阳. 复杂地质条件下公路隧道围岩监控量测与非确定性反分析研究[J]. 岩石力学与工程学报,2004,23(20):3 460–3 464.(JIANG Shuping,ZHAO Yang. Study on monitoring and back analysis of road tunnel with complex geology[J]. Chinese Journal of Rock Mechanics and Engineering,2004,23(20):3 460–3 464.(in Chinese))
[14] 张顶立,王梦恕,高 军,等. 复杂围岩条件下大跨隧道修建技术研究[J]. 岩石力学与工程学报,2003,22(2):290–296.(ZHANG Dingli,WANG Mengshu,GAO Jun,et al. Research on construction technology of large-span tunnel in complex rock[J]. Chinese Journal of Rock Mechanics and Engineering,2003,22(2):290–296.(in Chinese))
[15] 李利平,李术才,张庆松,等. 浅埋大跨隧道现场试验研究[J]. 岩石力学与工程学报,2007,26(增1):3 565–3 571.(LI Liping,LI Shucai,ZHANG Qingsong,et al. In-situ testing study on shallow buried large-span tunnel[J]. Chinese Journal of Rock Mechanics and Engineering,2007,26(Supp.1):3 565–3 571.(in Chinese)) |
| [1] |
MAO Yuting1, 2, HE Manchao1, 2, LIU Fangzhou3, BAI Xing4, YANG Xiaojie1, 2, TAO Zhigang1, 2*. Development and application of a large-scale physical model system for tunnel creep testing[J]. , 2026, 45(6): 1627-1638. |
|
|
|
|