Abstract By analyzing the mechanism of rock burst start-up,the blasting effect of the concentrated stress distribution in the roadway is studied by numerical simulation methods;and the dredging method of pressure with deep-hole interval blasting based on theory of rock burst start-up is proposed. The research results show that:(1) The interval of deep-hole blasting in roadway should be the area of rock burst start-up,otherwise it will play a negative role. (2) It is limited to dredge and debase concentrated stress by increasing intension of roadway support. (3) On one hand,the dredging method of pressure with deep-hole interval blasting can dredge and debase the degree of concentrated stress or energy of the area of rock burst start-up,thus the rock burst start-up step can be prevented. On other hand,it let the area of rock burst start-up firstly move to the deep coal wall;and the total energy which is consumed by rock burst start-up in dredging pressure area increases,but the energy release speed reduces. The good effect of application the research results to field engineering is got.
|
|
|
|
|