| INVESTIGATION OF GROUND PASS SHIELD TUNNELLING METHOD BASED ON LARGE-SCALE MODEL TEST AND ITS ENGINEERING APPLICATION |
| ZHANG Zixin1,2,HU Wen1,2,LIU Chao1,2,TENG Li3 |
| (1. Key Laboratory of Geotechnical and Underground Engineering of Ministry of Education,Tongji University,Shanghai 200092,China;2. Department of Geotechnical Engineering,Tongji University,Shanghai 200092,China;3. Shanghai Urban Construction(Group) Corporation,Shanghai 200023,China) |
|
|
|
|
Abstract The creation of ground pass shield tunnelling(GPST) method has conquered the disadvantage of constructing working shaft for shield launching and arrival which is a typical of traditional tunnelling method,and making an innovative turning point on shield tunnelling history. This paper first presents a detail investigation on the key problems of GPST method by adopting large-scale model test,numerical simulation and in-situ monitoring. The surface settlement characteristics of different crossing stages of GPST method have been revealed. In addition,an engineering application of this new method was carried out in Moling-Jiangjun interval of Nanjing intercity fast track;some key tunnelling parameters and effective measures were explored. Comparison was also done between the monitoring data,model test results and numerical results;it is shown a good agreement with each other;and a sound basis is established for the broad application of GPST method.
|
|
Received: 20 May 2013
|
|
|
|
|
|
|