| A METHOD OF METRO ADVANCED GEOLOGICAL PREDICTION UNDER KARST GEOLOGY CONDICTION |
| SU Maoxin,QIAN Qihu,LI Shucai,XUE Yiguo,ZHANG Qingsong,QIU Daohong,NIE Lichao |
| (Geotechnical and Structural Engineering Research Center,Shandong University,Jinan,Shandong 250061,China) |
|
|
|
|
Abstract Compared to the normal road or railway tunnels,metro passed through the stratum over the road,so that the metro advanced prediction(mainly geophysical class prediction) implementation can be divided into two parts:prediction inside and outside the tunnel. However,due to shallow depth of the metro and many factors of interference,it?s need to use the comprehensive advanced prediction. By analyzing the metro characters under the karst geological conditions,using the advantages of ground penetrating radar(GPR) and resistivity tomography,a comprehensive prediction method is proposed to carry out GPR forecasts inside and carry out the forecasts of the combination of resistivity tomography and GPR method outside;then through an engineering application,a detailed analysis of the implementation of comprehensive and comprehensive forecasting methods is made to prove that the comprehensive prediction method is effective for metro advanced prediction under the conditions of karst geology.
|
|
Received: 08 February 2011
|
|
|
|
| [1] 李术才,李树忱,张庆松,等. 岩溶裂隙水与不良地质情况超前预报研究[J]. 岩石力学与工程学报,2007,26(2):217–225.(LI Shucai,LI Shuchen,ZHANG Qingsong,et al. Forecast of karst fractured groundwater and defective geological conditions[J]. Chinese Journal of Rock Mechanics and Engineering,2007,26(2):217–225.(in Chinese))
[2] 李术才,薛翊国,张庆松,等. 高风险岩溶地区隧道施工地质灾害综合预报预警关键技术研究[J]. 岩石力学与工程学报,2008,27(7):1 297–1 307.(LI Shucai,XUE Yiguo,ZHANG Qingsong,et al. Key technology study on comprehensive prediction andearly- warning of geological hazards during tunnel construction in high-risk karst areas[J].Chinese Journal of Rock Mechanics and Engineering,2008,27(7):1 297–1 307.(in Chinese))
[3] 王梦恕. 对岩溶地区隧道施工水文地质超前预报的意见[J]. 铁道勘查,2004,(1):7–10.(WANG Mengshu. Hydrogeological and geological forecast of tunnel construction in the karst district[J]. Railroad Survey,2004,(1):7–10.(in Chinese))
[4] 钟世航. TSP作隧道掌子面前方地质预报几例失误原因分析[J]. 岩石力学与工程学报,2003,22(增1):2 443–2 446.(ZHONG Shihang. Analysis on the failure reasons in survey forward from working face of tunnels by means of TSP[J]. Chinese Journal of Rock Mechanics and Engineering,2003,22(Supp.1):2 443–2 446.(in Chinese))
[5] 薛翊国,李术才,张庆松,等. TSP超前预报系统探测岩溶隧道的应用研究[J]. 地下空间与工程学报,2007,21(6):1 187–1 191. (XUE Yiguo,LI Shucai,ZHANG Qingsong,et al. Application of TSP advanced prediction to tunnel in karst areas[J]. Chinese Journal of Underground Space and Engineering,2007,21(6):1 187–1 191.(in Chinese))
[6] 刘传孝. 探地雷达空洞探测机制研究及应用实例分析[J]. 岩石力学与工程学报,2000,19(2):238–241.(LIU Chuanxiao. Study on mechanism of cavity detection by GPR and the analysis of its application examples[J]. Chinese Journal of Rock Mechanics and Engineering,2000,19(2):238–241.(in Chinese))
[7] 苏茂鑫,李术才,薛翊国,等. 隧道掌子面前方低阻夹层的瞬变电磁探测研究[J]. 岩石力学与工程学报,2010,29(增1):2 645– 2 650.(SU Maoxin,LI Shucai,XUE Yiguo,et al. The detection of low resistivity interbed in front of the tunnel face by the means of TEM[J]. Chinese Journal of Rock Mechanics and Engineering,2010,29(增1):2 645–2 650. (in Chinese))
[8] 雷明锋,彭立敏,施成华. 复杂地质条件下隧道浅埋段全空间综合超前地质预报技术[J]. 岩石力学与工程学报,2009,28(增2):3 571– 3 576.(LEI Mingfeng,PENG Limin,SHI Chenghua. Whole space comprehensive advanced geological prediction technique for shallow-buried section of tunnel under complicated geological condition[J]. Chinese Journal of Rock Mechanics and Engineering,2009,28(Supp.2):3 571–3 576.(in Chinese))
[9] 刘文祥,鲁来玉,石 桂,等. 综合物探在地铁隧道工程建设中的应用[J]. 物探与化探,2004,28(2):181–183.(LIU Wenxiang,LU Laiyu,SHI Gui,et al. The application of integrated geophysical exploration to the light-rail tunnel construction[J]. Geophysical and Geochemical Exploration,2004,28(2):181–183.(in Chinese))
[10] 刘浩杰,白明洲. 探地雷达在城市地铁工程中的应用[J]. 物探与化探,2006,30(3):280–282.(LIU Haojie,BAI Minzhou. The application of the ground probing radar to urban subway construction[J]. Geophysical and Geochemical Exploration,2006,30(3):280–282. (in Chinese))
[11] 陈荣泰. 地铁浅埋暗挖隧道施工超前地质预报的技术方法[J]. 广州建筑,2007,(1):23–27.(CHEN Rongtai. Advanced technical method geological forecast for the construction of shallowly buried and undermined tunnel for metro building[J]. Guangzhou Architecture,2007,(1):23–27.(in Chinese))
[12] 李天斌,孟陆波,朱 劲,等. 隧道超前地质预报综合分析方法[J]. 岩石力学与工程学报,2009,28(12):2 429–2 436.(LI Tianbin,MENG Lubo,ZHU Jin,et al. Comprehensive analysis method for advanced forecast of geology in tunnels[J]. Chinese Journal of Rock Mechanics and Engineering,2009,28(12):2 429–2 436.(in Chinese)) |
|
|
|