TUNNELING IN SQUEEZING GROUND CONDITIONS:WITH A CASE STUDY OF YANMENGUAN RAILWAY TUNNEL
XU Zailiang1,SUN Yuanchun1,2
(1. The 3rd Railway Survey and Design Institute Group Corporation,Tianjin 300142,China;2. School of Civil Engineering, Southwest Jiaotong University,Sichuan,Chengdu 610031,China)
Abstract:Squeezing rock refers to weak rock under high grostress,so squeezing ground conditions conclude high grostress and weak rock,it means large convergences of the tunnel walls. Squeezing ground conditions have posed and continue to pose a major obstacle to the construction of tunnels through mountains. The Yanmenguan railway links the city of Datong to Yuanping in China through the Hengshan mountains. The tunnel is 14.1 km long with a two lane horse-shoe section,which is excavated in Archean plagioclase gneiss and granitic gneiss at depths of up to 820 m below surface,and extreme squeezing problems have been encountered,especially in sections of DK121+203–DK121+175. Based on analysis of engineering geological conditions,stability of surrounding rock and deformation monitoring,it is found that:(1) The sections of DK121+203–DK121+175 locate at fracture zones of ancient metamorphic rocks. (2) Rock mass quality and geostress conditions are key factors for the stability of surrounding rock. (3) Surrounding rock deformation sharply increased mainly due to excavation of middle,under bench and invert. (4) The effect is obvious to control surrounding rock deformation by strengthening the primary support and radial grouting behind primary support.
许再良1,孙元春1,2. 雁门关铁路隧道挤压变形问题分析[J]. 岩石力学与工程学报, 2014, 33(S2): 3834-3839.
XU Zailiang1,SUN Yuanchun1,2. TUNNELING IN SQUEEZING GROUND CONDITIONS:WITH A CASE STUDY OF YANMENGUAN RAILWAY TUNNEL. , 2014, 33(S2): 3834-3839.
叶圣教. 辛普伦铁路隧道的施工和回顾[M].成都:西南交通大学出版社,1995:120-134.(YE Shengjiao. Review of Simplon railway tunnel construction[M].Chengdu:Southwest Jiaotong University Press,1995:120-134.(in Chinese))
[2]
BARLA G.Squeezing rocks in tunnels[J].ISRM News Journal,1995,3(4):44-49.
[3]
SINGH B,GOEL R K,JETHWA J L,et al. Support pressure assessment in arched underground openings through poor rock masses[J]. EngineeringGeology,1997,48(1/2):59-81.
[4]
喻渝.挤压性围岩支护大变形的机制及判定方法[J].世界隧道,1998,(1):46-51.(YU Yu. Serious deformation of surrounding rock insqueezing ground[J].WorldTunnel,1998,(1):46-51.(in Chinese))
[5]
孙元春,张巍.挤压性隧道围岩变形分级研究综述[J].现代隧道技术,2011,48(增):42-47.(SUN Yuanchun,ZHANG Wei.Review on classification method of squeezing deformation in tunnels[J].ModernTunnelling Technology,2011,48(Supp.):42-47.(in Chinese))
[6]
关宝树.隧道施工要点集[M].北京:人民交通出版社,2003:389-403.(GUAN Baoshu. Key points set of tunnel construction[M].Beijing:China Communications Press,2003:389-403.(in Chinese))
[7]
刘高,张帆宇,李新召,等.木寨岭隧道大变形特征及机制分析[J].岩石力学与工程学报,2005,24(Supp.2):5521-5526.(LIU Gao,ZHANG Fanyu,LIU Xinzhao,et al.Research on large deformation and its mechanism of Muzhailing tunnel[J].Chinese Journal of Rock Mechanics and Engineering,2005,24(Supp.2):5521-5526.(in Chinese))
[8]
刘志春,朱永全,李文江,等.挤压性围岩隧道大变形机制及分级标准研究[J].岩土工程学报,2008,30(5):690-697.(LIU Zhichun,ZHU Yongquan,LI Wenjiang,et al.Mechanism and classification criterion for large deformation of squeezing ground tunnels[J].Chinese Journal of Geotechnical Engineering,2008,30(5):690-697.(in Chinese))
[9]
孙元春. 挤压性围岩变形机制及其控制技术研究[博士学位论文][D].北京:中国科学院地质与地球物理研究所,2010.(SUN Yuanchun.Research on mechanism and controlling technologies of surrounding rock in sqeezing ground[Ph. D. Thesis][D]. Beijing:Institute of Geology and Geophysics,Chinese Academey of Sciences,2010.(in Chinese))
[10]
林达明,尚彦军,陈明星,等.雁门关隧道大变形突泥段地质结构与力学分析[J].岩石力学与工程学报,2012,31(增1):2751-2757.(LIN Daming,SHANG Yanjun,CHEN Mingxing,et al.Geological structures and mechanical analysis of large-deformation mud bursting section in Yanmengguan tunnel[J].Chinese Journal of Rock Mechanicsand Engineering,2012,31(Supp.1):2751-2757.(in Chinese))
[11]
铁道第三勘察设计院集团有限公司.雁门关隧道工程地质勘察报告[R].天津:铁道第三勘察设计院集团有限公司,2007.(The3rd Railway Survey and Design Institute Group Corporation. Reporton engineeringgeological investigation of Yanmenguan tunnel[R].Tianjin:The 3rd Railway Survey and Design Institute GroupCorporation,2007.(in Chinese))
[12]
孙元春,高波,许再良,等.隧道围岩挤压变形预测方法研究[J].铁道工程学报,2012,161(2):50-54.(SUN Yuanchun,GAO Bo,XU Zailiang,et al.Research on prediction method of squeezing deformation of surrounding rock oftunneling[J].Journal of Railway EngineeringSociety,2012,161(2):50-54.(in Chinese))
[13]
中华人民共和国铁道部.高速铁路隧道工程施工技术指南[M].北京:中国铁道出版社,2010:47-50.(Ministry of Railways of the P.R.C.Technical guide for construction of high-speed railway tunnel engineering[M].Beijing:China Railway Publishing House,2010:47-50.(in Chinese))
[14]
吕庆,孙红月,尚岳全.强度折减有限元法中边坡失稳判据的研究[J].浙江大学学报:工学版,2008,42(1):83-87.(LU Qing,SUNHongyue,SHANG Yuequan.Slope failure criteria of shear strengthreduction finite element method[J].Journal of Zhejiang University:Engineering Science,2008,42(1):83-87.(in Chinese))