[1] 陈清运,邓 雄,刘美山,等. 采用聚能爆破技术治理岩爆灾害的试验研究[J]. 黄金,2011,(3):29–32.(CHEN Qingyun,DENG Xiong, LIU Meishan,et al. Experimental investigation on solving rock burst problem by assembling energy blasting technique[J]. Gold,2011,(3):29–32.(in Chinese))
[2] 刘美山,杨 建,葛文辉,等. 锦屏二级水电站引水隧洞岩爆灾害的工程治理方法研究[J]. 贵州水力发电,2010,24(5):11–15.(LIU Meishan,YANG Jian,GE Wenhui,et al. Engineering solving means investigation of rock burst calamity in diversion tunnel at Jinping two-stage power station [J]. Guizhou Water Power,2010,24(5):11–15.(in Chinese))
[3] 刘美山,杨 建,葛文辉,等. 锦屏二级水电站2#引水隧洞爆破治理岩爆试验研究[J]. 工程爆破,2011,17(2):8–11.(LIU Meishan, YANG Jian,GE Wenhui,et al. Experimental investigation of solving rock burst by blasting means in diversion tunnel #2 at Jinping two-stage power station[J]. Engineering Blasting,2011,17(2):8–11.(in Chinese))
[4] 王 平,刘士恩. 解除应力爆破结合柔性支护系统在锦屏电站的应用[J]. 西部探矿工程,2009,(12):151–155.(WANG Ping,LIU Shien. Application of stress relieve blasting combined with flexible supporting system at Jinping power station[J]. West China Exploration Engineering,2009,(12):151–155.(in Chinese))
[5] 吴建福. 锦屏辅助洞岩爆洞段施工技术措施[J]. 西部探矿工程,2008,(10):199–201.(WU Jianfu. Construction technical measures of auxiliary tunnel rock burst section at Jinping power station[J]. West China Exploration Engineering,2008,(10):199–201.(in Chinese))
[6] 朱焕春. 锦屏二级辅助洞岩爆控制现场工作总结报告[R]. 成都:二滩水电开发有限主任公司,2008.(ZHU Huanchun. Rock burst control summary report of field work at auxiliary tunnel in Jinping power station[R]. Chengdu:Ertan Hydropower Development Company,Ltd.,2008.(in Chinese))
[7] 汪 洋,王继敏,尹健民,等. 基于快速应力释放的深埋隧洞岩爆防治对策研究[J]. 岩土力学,2012,33(2):547–553.(WANG Yang,WANG Jimin,YIN Jianmin,et al. Research on prevention measures of rock burst based on rapid stress release in deep tunnel[J]. Rock and Soil Mechanics,2012,33(2):547–553.(in Chinese))
[8] 陈智强,张永兴,周检英. 开挖诱发隧道围岩变形的红外热像试验研究[J]. 岩土工程学报,2012,34(7):1 271–1 277.( CHEN Zhiqiang, ZHANG Yongxing, ZHOU Jianying. Experimental study on infrared photographs of deformation and failure of surrounding rock of tunnels procession induced by excavation[R]. Chinese Journal of Geotechnical Engineering,2012,34(7):1 271–1 277.(in Chinese))
|