| Study On Slurry Balanced Pipe Jacking Construction & Its Parameters |
| By Fu, Deming; Lou, Ruyue |
| Technical Center, STEC |
|
|
|
|
Abstract Contract 1.1 of Shanghai Sewerage Implementation Project II stage was a work job to cross the Huangpu River as an inverted siphon, where EP requirements have been strict, and work execution difficult. This article presents ,in particular ,the application in this project ,of the first slurry balanced pipe jacking machine in China and a study on construction parameters for slurry balanced pipe jacking operation in order to find the behavior of ground settlement caused by it.
|
|
Received: 31 March 2003
|
|
|
|
|