MODIFICATION AND DEVELOPMENT OF CHARACTERISTIC LINE METHOD OF TUNNEL
ABI Erdi1,2,ZHENG Yingren2,FENG Xiating1,XIANG Yuzhou2
(1. State Key Laboratory of Geomechanics and Geotechnical Engineering,Institute of Rock and Soil Mechanics,Chinese Academy of Sciences,Wuhan,Hubei 430071,China;2. Department of Architectural Engineering,Logistical Engineering University of PLA,Chongqing 400041,China)
Abstract:The traditional characteristic line method takes the preliminary lining as elastic component. But infact so the deformation of preliminary lining in practical tunnel engineering is much bigger than elastic deformation and the preliminary lining would be in the plastic state. Preliminary lining is considered as elastic-plastic materials to correct the traditional characteristic line method and numerical limit analysis is conducted to work out the safety factor of tunnel surrounding rock. Thus the corrected characteristic curve of surrounding rock and the pressure on the surrounding rock and preliminary lining can be obtained through strict mechanic calculation. The corrected characteristic line method through numerical limit analysis based on FEM strength reduction can solve the problem of design and calculation of tunnel engineering quantitatively,which provides theoretical basis and calculation method for the tunnel design.
阿比尔的1,2,郑颖人2,冯夏庭1,向钰周2. 隧道特征线法的修正与发展[J]. 岩石力学与工程学报, 2015, 34(s1): 3067-3073.
ABI Erdi1,2,ZHENG Yingren2,FENG Xiating1,XIANG Yuzhou2. MODIFICATION AND DEVELOPMENT OF CHARACTERISTIC LINE METHOD OF TUNNEL. , 2015, 34(s1): 3067-3073.
中华人民共和国行业标准编写组. JTG D70—2004公路隧道设计规范[S]. 北京:人民交通出版社,2004.(The Professional Standards Compilation Group of People?s Republic of China. JTG D70—2004 Code for design of road tunnel[S]. Beijing:China Communications Press,2004.(in Chinese))
Your browse does not support frame!