Abstract The freezing method for the construction of connected aisle in Nanjing metro project is studied. During construction,the temperature in the salty water and frozen soil,the deformation of ground surface and tunnel were measured. Based on the measurement,the variation rules of the above variables are revealed and investigated and a guidance on the freezing method for the construction of connected aisle is proposed.
|
|
Received: 24 May 2003
|
|
|
|
| [1] |
MAO Yuting1, 2, HE Manchao1, 2, LIU Fangzhou3, BAI Xing4, YANG Xiaojie1, 2, TAO Zhigang1, 2*. Development and application of a large-scale physical model system for tunnel creep testing[J]. , 2026, 45(6): 1627-1638. |
|
|
|
|