Modification of Hoek-Brown criterion and its application
LI Shuobiao1,2,XUE Yadong1,2
(1. Key Laboratory of Geotechnical and Underground Engineering of Ministry of Education,Tongji University, Shanghai 200092,China;2. Department of Geotechnical Engineering,Tongji University,Shanghai 200092,China)
Abstract:Hoek-Brown failure criterion has prominent advantages. However,when using the criterion,it is difficult to accurately obtain disturbed factor D and geological strength index GSI-value,that are the two main parameters in the criterion. According to this,This paper puts forward a convenient and accurate method to determine the two parameters,after summary analyzing scholars improvements of the traditional Hoek-Brown criterion. To get the disturbed factor D,this paper uses the square of ration between P-wave velocity of rock mass and rock. Then to obtain the GSI-value,this paper uses the relationship between the P-wave and rock mass rating RMR-value. Further,This paper puts the formulas of D and GSI into Hoek-Brown criterion to obtain a new modified criterion. In order to verify the modified criterion is reasonable,rock mass physical-mechanical parameters are respectively calculated by modified criterion and Hoek-Brown criterion for comparison,basing on the Yellow River Maerdang hydropower station dam foundation rock mass engineering case. The results of the two criterions show the same trend and the numeral difference is very small. Therefore,the modified criterion can satisfy the engineering application. Especially,it can be used to quickly and accurately calculate the two main parameters in Hoek-Brown criterion,and then calculate the mechanical parameters of rock mass.
李硕标1,2,薛亚东1,2. Hoek-Brown准则改进及应用[J]. 岩石力学与工程学报, 2016, 35(S1): 2732-2738.
LI Shuobiao1,2,XUE Yadong1,2. Modification of Hoek-Brown criterion and its application. , 2016, 35(S1): 2732-2738.
HOEK E,BROWN E T. Underground excavations in rock[M]. London:The Institute of Mining and Metallurgy,1980:183-241.
[2]
HOEK E. Strength of jointed rock masses[J]. Geotechnique,1983,33(3):187-223.
[3]
HOEK E. The Hoek-Brown failure criterion-a 1988 update[C]//Proceedings ofthe 15th Canadian Rock Mech. Symp. Toronto:Dept. Civil Engineering,University of Toronto,1988:31-38.
[4]
HOEK E,WOOD D,SHAH S. A modified Hoek-Brown criterion for jointed rock masses[C]//Proceedings ofRock Characterization,Symp. Int. Soc. Rock Mech. [S. l.]:[s. n.],1992:209-214.
[5]
HOEK E. Strength of rock and rock masses[J]. ISRM News Journal,1994,2(2):4-16.
[6]
HOEK E,KAISER P,BAWDEN WF. Support of underground excavations in hard rock[M]. Rotterdam:Balkema,1995:27-47.
[7]
HOEK E,BROWN E T. Practical estimates of rock mass strength[J]. International Journal of Rock Mechanics and Mining Sciences,1997,34(8):1165-1186.
[8]
HOEK E,CARRANZA-TORRES C,CORKUM B. Hoek-Brown failure criterion[C]//Proceedings of NARMS-Tac. [S. l.]:[s. n.],2002:267-273.
[9]
SONMEZ H,ULUSAY R. Modifications to the geological strength index(GSI) and their applicability to stability of slopes[J]. International Journal of Rock Mechanics and Mining Sciences,1999,36(6):743-760.
[10]
闫长斌,徐国元. 对Hoek-Brown公式的改进及其工程应用[J]. 岩石力学与工程学报,2005,24(22):4030-4035.(YAN Changbin,XU Guoyuan. Modification of Hoek-Brown expressions and its application to engineering[J].Chinese Journal of Rock Mechanics and Engineering,2005,24(22):4030-4035.(in Chinese))
[11]
夏开宗,陈从新,刘秀敏,等. 基于岩体波速的Hoek-Brown准则预测岩体力学参数方法及工程应用[J]. 岩石力学与工程学报,2013,32(7):1458-1465.(XIA Kaizong,CHEN Congxin,LIU Xiumin,et al.Estimation of rock mass mechanical parameters based on ultrasonic velocity of rock mass and Hoek-Brown criterion and its application to engineering[J]. Chinese Journal of Rock Mechanics and Engineering,2013,32(7):1458-1465.(in Chinese))
[12]
闫长斌. 爆破作用下岩体累积损伤效应及其稳定性研究[博士学位论文][D]. 长沙:中南大学,2006.(YAN Changbin. Study on cumulative damage effects and stability of rock mass under blasting loading[Ph. D. Thesis][D]. Changsha:Central South University,2006.(in Chinese))
[13]
SERAFIM J L,PEREIRA J P. Considerations of the gemechanics classification of Bieniawski[C]//Proceedings International Symposium Engineering Geology and Underground Construction. [S. l.]:[s. n.],1983:1133-1142.
[14]
BARTON N. Some new Q-value correlations to assist in site characterisation and tunnel design[J]. International Journal of Rock Mechanics and Mining Sciences,2002,39(2):185-216.
[15]
RUBIN A M,AHRENS T J. Dynamic tensile-failure-induced velocity deficits in rock[J]. Geophysical Research Letters,1991,18(2):219-222.
[16]
宋彦辉,巨广宏. 基于原位试验和规范的岩体抗剪强度与Hoek-Brown准则估值比较[J]. 岩石力学与工程学报,2012,31(5):1000-1006.(SONG Yanhui,JU Guanghong. Determination of rock mass shear strength based on in-situ tests and codes and comparison with estimation by Hoek-Brown criterion[J]. Chinese Journal of Rock Mechanics and Engineering,2012,31(5):1000-1006.(in Chinese))
[17]
黄吕卫. 玛尔挡水电站坝肩高边坡工程地质研究[硕士学位论文][D]. 兰州:兰州大学,2011.(HUANG Luwei. Engineering geological research on dam abutment high slope of Maerdang hydropower station[M. S. Thesis][D].Lanzhou:Lanzhou University,2011.(in Chinese))
[18]
巨广宏,吕生弟,宋彦辉,等. 黄河玛尔挡水电站坝基岩体强度特性与参数取值[J]. 人民长江,2011,42(9):50-54.(JU Guanghong,LUShengdi,SONG Yanhui,et al. Rock mass strength characteristics of dam foundation of Maerdang hydropower station on Yellow River and parameter determination[J].Yangtze River,2011,42(9):50-54.(in Chinese))